Park Ridge residents,
Below is the current paving schedule for Greenbriar Avenue and Hillcrest Drive.
The current paving schedule is as follows:
Wednesday, November 5: Complete binder placement for driveways and intersections
Thursday, November 6: Binder placement for the mainline
Friday, November 7: Begin surface coat of asphalt
Saturday (if needed), November 8: Complete surface coat
Additional details:
A-1 Excavating will be on-site Thursday to move garbage cans to avoid conflicts with paving and garbage collection.
"Mr. Manhole" is scheduled for Monday to finish sanitary manhole adjustments.
The final crew is expected Monday or Tuesday next week to complete grading and prepare for hydroseeding.