If you have questions during construction, please call:

Logan Pickruhn, Engineering Technician                        Thomas Turchi, Project Manager
715-571-7644                                                                  715-304-0462

* * * * * *

8/20/25 - UPDATE

WORK COMPLETED

The past 2 weeks A-1 has completed removals on Greenbriar and Hillcrest. The connection was made to the Stevens Point water main at State Highway 66 and the patch was poured. The water main has been installed on Greenbriar Ave and has started to be installed on Hillcrest Drive. Van Ert was on site to remove all light poles on the project. Mailboxes were moved to Crestwood Drive, behind the Village Hall. A detour has been set up for the Green Circle Trail.

UPCOMING WORK

Hillcrest Drive's water main will be completed and the crew will start to work on service laterals. Lateral location will be marked at the right of way with stakes painted blue. If there are any questions or concerns about lateral location, feel free to call, email, or text Logan, contact info is listed below.

MSA Contact Information

Onsite Project Representative

Logan Pickruhn

Phone: 715-304-0412

Cell: 715-571-7644

lpickruhn@msa-ps.com

 

Engineer

Tom Turchi

Phone: 715-304-0462

Cell: 715-486-6097

tturchi@msa-ps.com 

8/12/25 - UPDATE

Crew schedule:
We have an update regarding the construction schedule for this week:

🚧 A-1 Excavating Schedule
A-1 Excavating has confirmed they will remain on site for the rest of the week, as they no longer need to assist with another project.

💧 Water Main Installation – Greenbriar
Their goal is to complete installation of the water main on Greenbriar by the end of this week.

🔧 Lateral Installations – Hillcrest Drive
On Friday, crews plan to begin lateral installations on Hillcrest Drive, starting from Pinecrest Avenue to Sunset Avenue.

We appreciate your continued patience and cooperation as work progresses.

(posted 8/12/2025)

* * * * * *

8/12/25 — UPDATE REGARDING MAILBOXES & GARBAGE COLLECTION

📍 Mailbox Relocation
As work progresses, some mailboxes will need to be temporarily moved. The designated temporary location is near the Village Hall. MSA’s foreman is working to notify affected residents individually as these changes occur.

🗑️ Garbage and Recycling Collection
There will be no disruption to garbage and recycling service this week. Please continue placing your cans as you normally would.

Your patience and cooperation is greatly appreciated.

(posted 8/12/2025)

* * * * *

ALERT - Streetlight Electrical Work
As part of the Hillcrest Drive/Greenbriar Avenue road project, all Village streetlights south of Park Ridge Drive may experience occasional power outages during the week of 8/11/25.

The outages will occur while crews reconfigure the wiring to connect with junction boxes associated with the new “dark sky” streetlights being installed along Hillcrest Drive and the north half of Greenbriar Avenue. Thank you for your patience!

(posted 8/11/2025)

* * * * * *

The Hillcrest Drive-Greenbriar Avenue Street Reconstruction Project is scheduled to begin on July 29, with final completion set for November 7. As of this writing, the construction schedule is as follows:

July 29  Traffic control - Set-up of general traffic control notifying of road work and or closures (may change depending on project work needs; STH 66 work will likely be mid- to late August).

July 30   Mobilization – Moving equipment and supplies onsite.

July 31  Clearing and grubbing – Removal of trees shrubs, stumps and items within the right-of-way. 

August 7-8  Erosion control – Installation of silt fence and inlet protection.

August 7-8  Saw cutting - Sawing of asphalt, concrete and driveways prior to removals.

August  11-15  Removals – Removal of asphalt surfaces and portions of driveways. This may be staged throughout the project to reduce maintenance.

August  14-15  Electrical removals – Removal of the poles and electrical as identified on the plans. 

August  18-22   Watermain - Greenbriar – A-1 will begin watermain work on this street.  As of this writing, it was not yet determined when A-1 will complete the tie-in to the watermain on STH 66.

August  25-29  Watermain - Hillcrest – Following the watermain work on Greenbriar Avenue, work will begin on the watermain on Hilllcrest Drive.

August  27-Sept. 17  Common excavation - Excavation to subgrade and swale installation (cut and fill) as directed on the project design plans. Excavation will be followed closely with the placement of base course for the roadway structure.

September 2-11 Services – Installation of water services as shown on the plans. This will most likely take place before or during the “Common Excavation” work.

September  18-29  Electrical - Installation of the conduit, electrical wire, control panel and light poles per the plans. 

Sept. 30-Oct. 6  Concrete installation – Forming and placement of concrete per the plans (driveway aprons). I would assume that they will try to replace the concrete on STH 66 immediately after the tie in has been completed.

October 7-9  Asphalt installation – Placement of new asphalt streets and driveway aprons. 

October  10-17 Restoration   Placement of topsoil, seeding and mulching of the swale locations and or disturbed areas. 

October 20-21  Asphalt Surface – Final asphalt items. 

October 22-23  Painting - Painting of the chevrons for the speed table at Pinecrest and Hillcrest, stop bars, crosswalks and yellow curb.

November 7    Project completion

Posted 6/23/2025