The Hillcrest Drive-Greenbriar Avenue Street Reconstruction Project is scheduled to begin on July 29, with final completion set for November 7. As of this writing, the construction schedule is as follows:
July 29 Traffic control - Set-up of general traffic control notifying of road work and or closures (may change depending on project work needs; STH 66 work will likely be mid- to late August).
July 30 Mobilization – Moving equipment and supplies onsite.
July 31 Clearing and grubbing – Removal of trees shrubs, stumps and items within the right-of-way.
August 7-8 Erosion control – Installation of silt fence and inlet protection.
August 7-8 Saw cutting - Sawing of asphalt, concrete and driveways prior to removals.
August 11-15 Removals – Removal of asphalt surfaces and portions of driveways. This may be staged throughout the project to reduce maintenance.
August 14-15 Electrical removals – Removal of the poles and electrical as identified on the plans.
August 18-22 Watermain - Greenbriar – A-1 will begin watermain work on this street. As of this writing, it was not yet determined when A-1 will complete the tie-in to the watermain on STH 66.
August 25-29 Watermain - Hillcrest – Following the watermain work on Greenbriar Avenue, work will begin on the watermain on Hilllcrest Drive.
August 27-Sept. 17 Common excavation - Excavation to subgrade and swale installation (cut and fill) as directed on the project design plans. Excavation will be followed closely with the placement of base course for the roadway structure.
September 2-11 Services – Installation of water services as shown on the plans. This will most likely take place before or during the “Common Excavation” work.
September 18-29 Electrical - Installation of the conduit, electrical wire, control panel and light poles per the plans.
Sept. 30-Oct. 6 Concrete installation – Forming and placement of concrete per the plans (driveway aprons). I would assume that they will try to replace the concrete on STH 66 immediately after the tie in has been completed.
October 7-9 Asphalt installation – Placement of new asphalt streets and driveway aprons.
October 10-17 Restoration Placement of topsoil, seeding and mulching of the swale locations and or disturbed areas.
October 20-21 Asphalt Surface – Final asphalt items.
October 22-23 Painting - Painting of the chevrons for the speed table at Pinecrest and Hillcrest, stop bars, crosswalks and yellow curb.
November 7 Project completion
Posted 6/23/2025